Progress update at the No.03 project.

project
No.03

date
30.07.2024


At No. 03, construction is moving swiftly with the sunny weather enhancing the progress of three key extensions. The main rear extension's roof structure is now in place, casting beautiful shadows and framing large window openings that promise impressive views of the garden once completed. This extension is set to create a spacious area where the client can fully enjoy their outdoor surroundings.

The side extension, dedicated to upgrading the garage and adding a new utility and plant room, is also advancing well, with the walls now erected. This addition will provide enhanced functionality and storage space.

The smaller garden room extension, which features predominantly glass facades, is still in the early stages and remains at slab level. As this extension involves extensive glazing, it is expected to be the final part of the project to be completed.

Overall, the project at No. 03 is making excellent progress, with each extension contributing to a more functional and aesthetically pleasing home. The sunny weather has provided a perfect backdrop to the ongoing construction, highlighting the exciting changes and future potential of the property.

For the story of No.03 and its progress, visit the 'projects' page on our website.