CONSTRUCTION OVERVIEW
The construction period spanned a total of 5 months, during which the house underwent a comprehensive transformation of the house through a combination of demolition, new build, and refurbishment.
Initially, the project focused on the main new build element, which was the side extension. This was followed by the demolition of existing structures and spaces to facilitate new openings. In the final phase, refurbishment efforts concentrated on updating and enhancing existing areas.
This comprehensive approach ensured that the house was not only modernized but also seamlessly integrated with the new additions.
Month 01: Side Extension Foundations and Flooring
During Month 01, the primary focus was on the side extension. This involved essential groundwork, including the installation of foundations and below-ground drainage. Additionally, the team completed the beam and block floor, laying the foundation for the extension's structure.
Month 02: Progressing the Side Extension Walls and Roof
In Month 02, the focus continued on the side extension, with significant advancements made in constructing its walls and roof. The goal was to make the extension reasonably watertight, ensuring a solid and protected structure as the project moved forward.
Month 03: Interior Opening and Space Creation
In Month 03, the project's focus shifted to the interior opening works. Key tasks included removing specific walls and the existing fireplace to facilitate the creation of an expansive open-plan living area. This phase was essential for transforming the layout and enhancing the spatial flow of the home.
Month 04: Internal and External Openings Completed
In Month 04, significant progress was made with the internal openings of the side extension. Structural steels were installed and plasterboarding was completed, setting the stage for the final touches. On the exterior, openings were made for two picture windows and a large bifolding door, enhancing the extension's connectivity with the outside and preparing it for the next stages of the build.
Month 05: Underfloor Heating and Kitchen Installation
In Month 05, a concrete cutting machine was employed to carve out routes within the existing slab for underfloor heating pipes, ensuring efficient heat distribution. Following this, the installation of the kitchen units began, marking a key milestone in the project's progression and setting the foundation for the final touches in the new extension and the refurbished spaces.
Final Weeks: Finishing Touches
In the final weeks of the project, the focus was on essential finishing touches that bring the entire space together. This involved applying the final coats of paint to walls and ceilings, creating a polished and uniform appearance. The installation of door handles, locks, and other hardware was completed to ensure both functionality and aesthetic appeal. Flooring finishes were laid down, providing a durable and stylish surface throughout the space. Skirting boards were fitted to cover gaps between walls and floors, contributing to a clean and finished look. The kitchen worktop and focal breakfast bar were installed, finalizing the kitchen area and making it both practical and inviting.
These final elements ensured that the project was completed to a high standard, enabling the clients to fully enjoy their newly crafted spaces, which were designed to perfectly align with their lifestyle needs and preferences.